Appendix A.1: Unadjusted Unit Costs

Roadside Telecommunications (RS-TC)
Subsystem/Unit Cost Element IDAS No.[1] Lifetime (years)[2] Low Capital Cost ($K) High Capital Cost ($K) Cost Date Low O&M Cost ($K/year) High O&M Cost ($K/year) Cost Date Notes

DS0 Communication Line

TC001 20 0.5 1 1995 0.6 1.2 2003 56 Kbps capacity. Leased with typical distance from terminus to terminus of 8–15 miles, but most of the cost is not distance sensitive.
DS1 Communication Line TC002 20 0.5 1 1995 4.8 8.4 2002 1.544 Mbps capacity (T1 line). Leased with typical distance from terminus to terminus of 8–15 miles, but most of the cost is not distance sensitive.
DS3 Communication Line TC003 20 3 5 1995 24 72 2001 44.736 Mbps capacity (T3 line). Leased with typical distance from terminus to terminus of 8–15 miles, but most of the cost is not distance sensitive.
ISP Service Fee TC007 empty cell empty cell empty cell empty cell 0.18 0.6 2002 Monthly service fee ranges from $15 per month for regular dial-up service to $50 per month for DSL.
Direct Bury Armor Encased Fiber Cable empty cell empty cell 60 60 1999 0.02 0.02 1999 Cost is per mile. Includes cable and installation.
Conduit Design and Installation–Corridoring empty cell 20 50 65 2003 0.02 0.02 1999 Cost is per mile. Includes boring, trench, and conduit (3 or 4 inch). Cost would be significantly less for an aerial installation. In-ground installation would cost significantly less if implemented in conjunction with a construction project.
Twisted Pair Installation empty cell 20 12 12 1999 0.02 0.02 1999 Cost is per mile.
Fiber Optic Cable Installation empty cell 20 20 50 2003 0.02 0.02 1999 Cost is per mile for cable and in-ground installation. Cost would be significantly less for an aerial installation. In-ground installation would cost significantly less if implemented in conjunction with a construction project.
Cellular Communication empty cell empty cell 0.5 0.5 1999 0.3 0.4 1999 Cost is for one unit.
900 MHz Spread Spectrum Radio empty cell 10 9 9 1999 0.15 0.4 1999 Cost is per link.
Microwave Communication empty cell 10 10 20 2002 0.5 1 2002 Cost is per link. Cost could be higher depending on tower/antenna installation.
Wireless Communications, Low Usage TC004 empty cell empty cell empty cell empty cell 0.12 0.2 2003 125 Kbytes/month available usage (non-continuous use).
Wireless Communications, Medium Usage TC005 empty cell empty cell empty cell empty cell 0.6 0.7 1995 1,000 Kbytes/month available usage (non-continuous use).
Wireless Communications, High Usage empty cell 20 0.5 1 1995 1.2 1.8 2002 3,000 Kbytes/month available usage (non-continuous use).
Call Box empty cell 10 4 5.9 2002 0.714 0.714 1999 Capital cost includes call box and installation. O&M is cost per unit (per year) for service maintenance contract and annual cellular service fee.

Roadside Detection (RS-D)
Subsystem/Unit Cost Element IDAS No.[1] Lifetime (years)[2] Low Capital Cost ($K) High Capital Cost ($K) Cost Date Low O&M Cost ($K/year) High O&M Cost ($K/year) Cost Date Notes
Inductive Loop Surveillance on Corridor empty cell 5 3 8 2001 0.5 0.8 1995 Double set (four loops) with controller, power, etc.
Inductive Loop Surveillance at Intersection empty cell 5 9 16 2003 1 1.6 1999 Four legs, two lanes/approach.
Machine Vision Sensor on Corridor empty cell 10 21.7 29 2003 0.2 0.4 2003 One sensor both directions of travel. Does not include installation.
Machine Vision Sensor at Intersection empty cell 10 20 25.7 2003 0.2 0.5 2003 Four-way intersection, one camera per approach. Does not include installation.
Passive Acoustic Sensor on Corridor empty cell empty cell 3.7 8 2002 0.2 0.4 1998 Cost range is for a single sensor covering up to five lanes. Low cost is for basic sensor, which consists of the sensor, mounting kit, junction box, and cabinet termination card. High cost includes basic sensor with solar and wireless option. This option consists of an antenna, solar charger, battery, and panel, and wireless base station, which will handle up to eight sensors. Capital costs do not include installation or mounting structure.
Passive Acoustic Sensor at Intersection empty cell empty cell 5 15 2001 0.2 0.4 2002 Four sensors, four leg intersection.
Remote Traffic Microwave Sensor on Corridor empty cell 10 3.3 6 2002 0.1 0.1 2001 One sensor both directions of travel. Includes installation.
Remote Traffic Microwave Sensor at Intersection empty cell 10 18 empty cell 2001 0.1 0.1 2001 Four sensors, four leg intersection. Includes installation.
Infrared Sensor Active empty cell empty cell 6 7.5 2000 empty cell empty cell empty cell Sensor detects movement in two directions and determines vehicle speed, classification, and lane position.
Infrared Sensor Passive empty cell empty cell 0.7 1.2 2002 empty cell empty cell empty cell Sensor covers one lane and detects vehicle count, volume, and classification.
CCTV Video Camera RS007 10 7.5 17 2003 1.5 2.4 2001 Cost includes color video camera with pan, tilt, and zoom (PTZ). Includes installation.
CCTV Video Camera Tower RS008 20 4 12 2003 empty cell empty cell empty cell Low cost is for a 35 ft. tower. High cost is for 90 ft. tower. Includes foundation, pole, conduit, and labor.
Pedestrian Detection Microwave empty cell empty cell 0.6 0.6 2001 empty cell empty cell empty cell Cost is per device. Typical deployment consists of two devices per crosswalk for detection of pedestrian in crosswalk. Can be used for detection of pedestrian at the curbside.
Pedestrian Detection Infrared empty cell empty cell 0.3 0.5 2002 empty cell empty cell empty cell Cost is per device. Does not include installation. Typical deployment consists of two devices per crosswalk for detection of pedestrian at the sidewalk. Can be used for detection of pedestrian in the crosswalk.
Environmental Sensing Station (Weather Station) empty cell 25 30 50 2003 1.9 4.1 2003 Environmental Sensing Station (ESS), also known as a weather station, consists of pavement temperature sensor, subsurface temperature sensor, precipitation sensor (type and rate), wind sensor (speed and direction), air temperature and humidity sensors, visibility sensors, and remote processing unit (RPU). ESS provide condition data and are basic components of larger Road Weather Information Systems (see RWIS under TMC subsystem). RPU replaced every five years at $6.4K. O&M includes calibration, equipment repairs, and replacement of damaged equipment. O&M costs could be higher if state provided maintenance.
Traffic Camera for Red Light Running Enforcement empty cell empty cell 75 136 2001 60 60 2001 Low capital range is for a 35-mm wet film camera, which includes installation of the camera ($25K) and associated equipment (e.g., pole, loop detectors, cabinet foundation). High capital range is for digital camera, which includes a total of two cameras for a three-lane approach. O&M cost is for one 35-mm wet film camera per year. Note, most jurisdictions contract with a vendor to install and maintain, and process the back office functions of the RLR system. The vendor receives compensation from fines charged to violators.
Lowering System empty cell 20 8 10.5 2003 empty cell empty cell empty cell Cost includes the lowering system and the pole (pole height ranging 40 ft. to 70 ft.). Installation costs not included. The lowering system is mechanically operated; requires routine lubrication.
Portable Speed Monitoring System empty cell 15 5 15 2002 empty cell empty cell empty cell Trailer mounted two-digit dynamic message sign, radar gun, computer; powered by generator or operates off of solar power; and requires minimal operations and maintenance work. The system determines a vehicle's speed with the radar gun and displays the current speed, in real time, and also stores the speeds in a computer for further analysis.
Portable Traffic Management System empty cell empty cell 80 100 2003 empty cell empty cell empty cell This portable unit collects traffic data, communicates with a central control facility, and displays real-time traffic information to travelers. The system includes a trailer mounted dynamic message sign and mast equipped with a PTZ video camera, sensors, and wireless communications. Cost will vary depending on the type and number of traffic sensors installed.

Roadside Control (RS-C)
Subsystem/Unit Cost Element IDAS No.[1] Lifetime (years)[2] Low Capital Cost ($K) High Capital Cost ($K) Cost Date Low O&M Cost ($K/year) High O&M Cost ($K/year) Cost Date Notes
Linked Signal System LAN RS002 20 40 70 1995 0.4 0.8 1995 This element provides the connections to the linked signal system.
Signal Controller Upgrade for Signal Control RS003 20 2.5 6 2003 0.2 0.5 1995 Local controller upgrade to provide advanced signal control.
Signal Controller and Cabinet empty cell empty cell 8 15 2003 0.2 0.5 2001 Includes installation of traffic signal controller and cabinet per intersection.
Traffic Signal empty cell empty cell 95 115 2001 2.4 3 1999 Includes installation for one signal (four-leg intersection), conduit, controller, and detection device. Cost ranges from traffic signal with inductive loop detection (low) to non-intrusive detection (high).
Signal Preemption Receiver RS004 5 2 8 1995 0.05 0.2 1995 Two per intersection. Complement of IDAS elements RS005 and TV004.
Signal Controller Upgrade for Signal Preemption RS005 10 2 5 1995 empty cell empty cell empty cell Add-on to base capability (per intersection). Complement of IDAS elements RS004 and TV004.
Roadside Signal Preemption/Priority empty cell empty cell 2.5 5.5 2003 empty cell empty cell empty cell Includes infrared detector, detector cable, phase selector, and system software. Capital costs range is for two directions (low) and four directions (high). Does not include installation costs. Complement to transit (or emergency vehicle) on-board Signal Preemption/Priority Emitter.
Ramp Meter RS006 5 25 50 2003 1.2 2.8 2003 Includes ramp meter assembly, signal displays, controller, cabinet, detection, and optimization.
Software for Lane Control RS011 20 25 50 1995 2.5 5 1995 Software and hardware at site. Software is off-the-shelf technology and unit price does not reflect product development.
Lane Control Gates RS012 20 100 150 1995 2 3 1995 Per location.
Fixed Lane Signal RS009 20 6 8 1995 0.6 0.8 1995 Cost per signal.
Automatic Anti-Icing System Short Span empty cell 12 25 25 1998 2 2 1998 Typical automatic anti-icing system consists of a control system, chemical storage tank, distribution lines, pump, and nozzles. Pump and control hardware replaced every five years at cost of $3.5K. For a short span system ranging from 120 to 180 feet. O&M includes system maintenance, utilities, materials, and labor.
Automatic Anti-Icing System Long Span empty cell 12 50 495 1999 1.5 29.5 1999 Typical automatic anti-icing system consists of a control system, chemical storage tank, distribution lines, pump, and nozzles. Pump and control hardware replaced every five years at cost of $3.5K. For a long span system ranging from 320 feet to greater than 1/2 mile. O&M includes system maintenance, utilities, materials, and labor. The high O&M cost is for a much larger system, hence the need for a greater amount of materials.

Roadside Information (RS-I)
Subsystem/Unit Cost Element IDAS No.[1] Lifetime (years)[2] Low Capital Cost ($K) High Capital Cost ($K) Cost Date Low O&M Cost ($K/year) High O&M Cost ($K/year) Cost Date Notes
Roadside Message Sign RS010 20 50 75 1995 2.5 3.75 1995 Fixed message board for HOV and HOT lanes.
Wireline to Roadside Message Sign RS013 20 6 9 1995 empty cell empty cell empty cell Wireline to VMS (0.5 mile upstation).
Variable Message Sign RS015 20 48 120 2003 2.4 6 2003 Low capital cost is for smaller VMS installed along arterial. High capital cost is for full matrix, LED, three-line, walk-in VMS installed on freeway. Cost does not include installation.
Variable Message Sign Tower RS016 20 25 120 2003 empty cell empty cell empty cell Low capital cost is for a small structure for arterials. High capital cost is for a larger structure spanning three to four lanes. VMS tower structure requires minimal maintenance.
Variable Message Sign–Portable empty cell 14 21.5 25.5 2002 1.2 2 2000 Trailer mounted VMS (three-line, 8" character display); includes trailer, solar or diesel powered.
Highway Advisory Radio RS017 20 16 32 2001 0.6 1 2001 Capital cost is for a 10-watt HAR. Includes processor, antenna, transmitters, battery back-up, cabinet, rack mounting, lighting, mounts, connectors, cable, and license fee. Super HAR costs an additional $9–10K (larger antenna). Primary use of the super HAR is to gain a stronger signal.
Highway Advisory Radio Sign empty cell 10 5 9 2003 0.25 0.25 2003 Cost is for a HAR sign with flashing beacons. Includes cost of the controller.
Roadside Probe Beacon RS020 5 5 8 2001 0.5 0.8 2001 Two-way device (per location).
LED Countdown Signal empty cell 10 0.325 0.45 2001 empty cell empty cell empty cell Costs range from low (two 12 x 12-inch dual housing unit) to high (16 x 18-inch single housed unit). Signal indicates time remaining for pedestrian to cross, and a walk or don't walk icon. Countdown signals use low eight-watt LED bulbs, which require replacement approximately every five to seven years.
Pedestrian Crossing Illumination System empty cell 5 27.5 42 2003 2.75 4.2 2001 The capital cost range includes cost of equipment and installation. Equipment includes fixtures—four lamps per lane—for a three-lane crosswalk, controller, pole, and push button activator. Installation is estimated at 150–200% of the total equipment cost. Capital cost would be greater if the system included automated activation of the in-pavement lighting system. O&M is approximately 10% of the equipment cost.
Variable Speed Display Sign empty cell empty cell 3.7 5 2001 empty cell empty cell empty cell Low range is for a variable speed limit display system. High range includes static speed sign, speed detector (radar), and display system.

Roadside Rail Crossing (R-RC)
Subsystem/Unit Cost Element IDAS No.[1] Lifetime (years)[2] Low Capital Cost ($K) High Capital Cost ($K) Cost Date Low O&M Cost ($K/year) High O&M Cost ($K/year) Cost Date Notes
Rail Crossing Four-Quad Gate, Signals RS021 20 115 130 1995 4.25 4.85 1995 Gates and signals.
Rail Crossing Train Detector RS022 20 16 21.5 1995 0.77 1.03 1995 Train detector circuitry and communication line from intelligent interface controller (IIC) to wayside interface equipment (WIE). Assume two track crossing with two 0.5 mile communication lines.
Rail Crossing Controller RS023 10 8 10 1995 0.4 0.5 1995 Intelligent interface controller (IIC).
Rail Crossing Pedestrian Warning Signal, Gates RS024 20 10 15 1995 0.2 0.3 1995 Pedestrian warning signal and gates.
Rail Crossing Trapped Vehicle Detector RS025 10 25 30 1995 1.25 1.5 1995 Entrapped vehicle detection camera with poles and controller.

Parking Management (PM)
Subsystem/Unit Cost Element IDAS No.[1] Lifetime (years)[2] Low Capital Cost ($K) High Capital Cost ($K) Cost Date Low O&M Cost ($K/year) High O&M Cost ($K/year) Cost Date Notes
Entrance/Exit Ramp Meters empty cell 10 2 5 1995 0.2 0.5 1995 Ramp meters are used to detect and count vehicles entering/exiting the parking facility. O&M costs based on annual service contract.
Tag Readers empty cell 10 2 5 1995 0.2 0.5 1995 Readers support electronic payment scheme. O&M costs based on annual service contract.
Database and Software for Billing and Pricing empty cell 10 10 15 1995 1 2 1995 Database system contains parking pricing structure and availability. O&M costs based on annual service contract.
Parking Monitoring System empty cell 10 21 46 1998 empty cell empty cell empty cell Includes installation, detectors, and controllers.

Toll Plaza (TP)
Subsystem/Unit Cost Element IDAS No.[1] Lifetime (years)[2] Low Capital Cost ($K) High Capital Cost ($K) Cost Date Low O&M Cost ($K/year) High O&M Cost ($K/year) Cost Date Notes
Electronic Toll Reader TP001 10 2 5 2001 0.2 0.5 2001 Readers (per lane). O&M is estimated at 10% of capital cost.
High-Speed Camera TP002 10 7 10 2003 0.5 1 1995 Cost includes one camera/two lanes.
Electronic Toll Collection Software TP003 10 5 10 1995 empty cell empty cell empty cell Includes COTS software and database.
Electronic Toll Collection Structure TP004 20 10 15 1995 empty cell empty cell empty cell Mainline structure.

Remote Location (RM)
Subsystem/Unit Cost Element IDAS No.[1] Lifetime (years)[2] Low Capital Cost ($K) High Capital Cost ($K) Cost Date Low O&M Cost ($K/year) High O&M Cost ($K/year) Cost Date Notes
CCTV Camera RM001 7 2.1 5 2003 0.1 0.25 2003 Interior fixed mount camera for security. Low cost represents black and white pan/tilt/zoom (PTZ). High cost represents color PTZ. Does not include installation.
Integration of Camera with Existing Systems RM002 10 2 2.5 1995 empty cell empty cell empty cell Per location.
Informational Kiosk RM003 7 12 25 2001 1.2 5 1998 Includes hardware, enclosure, installation, modem server, and map software.
Integration of Kiosk with Existing Systems RM004 7 2.2 27.4 1995 empty cell empty cell empty cell Software costs are for COTS (low) and developed/outdoor (high).
Kiosk Upgrade for Interactive Usage RM005 5 5 8 1995 0.5 0.8 1995 Interactive information display interface (upgrade from existing interface).
Kiosk Software Upgrade for Interactive Usage RM006 5 10 12 1995 empty cell empty cell empty cell Software is COTS.
Transit Status Information Sign empty cell 10 4 8 2002 empty cell empty cell empty cell A LED display installed at transit terminal that provides status information on transit arrival. Cost depends on quality, size, and controller capabilities.
Smart Card Vending Machine RM007 5 37 40 1995 1.85 2 1995 Ticket vending machine for smart card.
Software, Integration for Smart Card Vending RM008 20 3 5 1995 empty cell empty cell empty cell Software is COTS.

Emergency Response Center (ER)
Subsystem/Unit Cost Element IDAS No.[1] Lifetime (years)[2] Low Capital Cost ($K) High Capital Cost ($K) Cost Date Low O&M Cost ($K/year) High O&M Cost ($K/year) Cost Date Notes
Basic Facilities, Comm for Large Area EM006 empty cell 4,000 4,000 1995 400 600 1995 For population >750,000. Based on purchase of building rather than leasing space. Communications includes communications equipment internal to the facility such as equipment racks, multiplexers, modems, etc.
Basic Facilities, Comm for Medium Area EM007 empty cell 3,200 3,200 1995 400 480 1995 For population <750,000 and >250,000. Based on purchase of building rather than leasing space. Communications includes communications equipment internal to the facility such as equipment racks, multiplexers, modems, etc.
Basic Facilities, Comm for Small Area EM008 empty cell 2,800 2,800 1995 400 420 1995 For population <250,000. Based on purchase of building rather than leasing space. Communications includes communications equipment internal to the facility such as equipment racks, multiplexers, modems, etc.
Emergency Response Hardware EM001 5 6 9 2003 0.12 0.18 2003 Includes three workstations. O&M is estimated at 2% of capital cost.
Emergency Response Software EM002 10 70 150 1995 0.5 3.5 1995 Includes emergency response plans database, vehicle tracking software, and real-time traffic coordination.
Emergency Response Labor EM003 empty cell empty cell empty cell empty cell 50 165 1995 Two people. Salary costs are fully loaded including salary, overtime, overhead, benefits, etc.
Emergency Management Communications Software EM004 20 5 10 1995 2.5 5 1995 Shared database between four sites. Cost is per site; software is COTS.
Hardware, Software Upgrade for E-911 and Mayday EM005 10 105 180 1995 1.7 2.5 1995 Data communications translation software, E911 interface software, processor, and three workstations.
800 MHz. Two-way Radio empty cell 5 0.8 1.7 2001 0.09 0.12 2001 Cost is per radio.

Emergency Vehicle On-Board (EV)
Subsystem/Unit Cost Element IDAS No.[1] Lifetime (years)[2] Low Capital Cost ($K) High Capital Cost ($K) Cost Date Low O&M Cost ($K/year) High O&M Cost ($K/year) Cost Date Notes
Communications Interface EV001 10 0.3 2 1995 0.02 0.02 1995 Emergency vehicle communications. Cost is per vehicle.
Signal Preemption/Priority Emitter empty cell empty cell 0.5 2.1 2003 empty cell empty cell empty cell Data-encoded emitter; manually initiated. Complement to Roadside Signal Preemption/Priority (see Roadside Control subsystem).

Information Service Provider (ISP)
Subsystem/Unit Cost Element IDAS No.[1] Lifetime (years)[2] Low Capital Cost ($K) High Capital Cost ($K) Cost Date Low O&M Cost ($K/year) High O&M Cost ($K/year) Cost Date Notes
Basic Facilities, Comm for Large Area IS019 empty cell 4,000 4,000 1995 400 600 1995 For population >750,000 (stand-alone). Based on purchase of building rather than leasing space. Communications includes communications equipment internal to the facility such as equipment racks, multiplexers, modems, etc.
Basic Facilities, Comm for Medium Area IS020 empty cell 3,200 3,200 1995 400 480 1995 For population <750,000 and >250,000 (stand-alone). Based on purchase of building rather than leasing space. Communications includes communications equipment internal to the facility such as equipment racks, multiplexers, modems, etc.
Basic Facilities, Comm for Small Area IS021 empty cell 2,800 2,800 1995 400 420 1995 For population <250,000 (stand-alone). Based on purchase of building rather than leasing space. Communications includes communications equipment internal to the facility such as equipment racks, multiplexers, modems, etc.
Information Service Provider Hardware IS001 5 26 35 2003 0.5 0.7 2003 Includes two servers and five workstations. O&M is estimated at 2%; could be higher for responsive and preventative maintenance.
Systems Integration IS017 20 90 110 1998 empty cell empty cell empty cell Integration with other systems.
Information Service Provider Software IS002 20 275 550 1995 13.75 27.5 1995 Includes database software (COTS) and traffic analysis software.
Map Database Software IS003 2 15 30 2003 empty cell empty cell empty cell Software is COTS.
Information Service Provider Labor IS004 empty cell empty cell empty cell empty cell 175 250 1995 Two staff at $50K to $75K and one staff at $75K to $100K. Salary cost are fully loaded prices and include base salary, overtime, overhead, benefits, etc.
FM Subcarrier Lease IS005 empty cell empty cell empty cell empty cell 120 240 1995 Cost is per year.
Hardware Upgrade for Interactive Information IS006 5 12 16 2003 0.24 0.32 2003 Includes one server and two workstations. O&M is estimated at 2%; could be higher for responsive and preventative maintenance.
Software Upgrade for Interactive Information IS007 20 250 500 1995 12.5 25 1995 Trip planning software (includes some development costs).
Added Labor for Interactive Information IS008 empty cell empty cell empty cell empty cell 100 150 1995 One staff at $50K to $75K for two shifts. Salary cost are fully loaded prices including base salary, overtime, overhead, benefits, etc.
Software Upgrade for Route Guidance IS009 20 250 500 1995 12.5 25 1995 Route selection software. Software is COTS.
Map Database Upgrade for Route Guidance IS010 2 100 200 1995 empty cell empty cell empty cell Map database software upgrade.
Hardware Upgrade for Emergency Route Planning IS011 5 8 10 2003 0.16 0.2 2003 Includes one server. O&M is estimated at 2%; could be higher for responsive and preventative maintenance.
Software Upgrade for Emergency Route Planning IS012 20 50 100 1995 2.5 5 1995 Route guidance software. Software is COTS.
Hardware Upgrade for Dynamic Ridesharing IS013 5 4 6 2003 0.08 0.12 2003 Includes two workstations. O&M is estimated at 2%; could be higher for responsive and preventative maintenance.
Software Upgrade for Dynamic Ridesharing IS014 20 100 200 1998 5 10 1995 Software includes some development cost.
Added Labor for Dynamic Ridesharing IS015 empty cell empty cell empty cell empty cell 100 150 1995 One staff at $50K to $75K for two shifts. Salary cost are fully loaded prices including base salary, overtime, overhead, benefits, etc.
Liability Insurance for Dynamic Ridesharing IS016 empty cell empty cell empty cell empty cell 50 100 1995 $50K to $100K per year.
Software Upgrade for Probe Information Collection IS018 20 250 500 1995 12.5 25 1995 Software includes COTS and some development cost.

Transportation Management Center (TM)
Subsystem/Unit Cost Element IDAS No.[1] Lifetime (years)[2] Low Capital Cost ($K) High Capital Cost ($K) Cost Date Low O&M Cost ($K/year) High O&M Cost ($K/year) Cost Date Notes
Basic Facilities, Comm for Large Area TM040 empty cell 3,500 8,000 2003 350 1,200 2003 For population >750,000. Based on purchase of building rather than leasing space. Communications includes communications equipment internal to the facility such as equipment racks, multiplexers, modems, etc. O&M is estimated at 10–15% of the capital cost.
Basic Facilities, Comm for Medium Area TM041 empty cell 3,200 3,200 1995 400 480 1995 For population <750,000 and >250,000. Based on purchase of building rather than leasing space. Communications includes communications equipment internal to the facility such as equipment racks, multiplexers, modems, etc. O&M is estimated at 10–15% of the capital cost.
Basic Facilities, Comm for Small Area TM042 empty cell 2,800 2,800 1995 400 420 1995 For population <250,000. Based on purchase of building rather than leasing space. Communications includes communications equipment internal to the facility such as equipment racks, multiplexers, modems, etc. O&M is estimated at 10–15% of the capital cost.
Hardware for Signal Control TM001 5 18.5 28.5 2003 9 10.5 2003 Includes one server and multiple workstations. O&M includes responsive and preventative maintenance.
Software, Integration for Signal Control TM006 5 105 150 2003 150 150 2003 Software and integration for a large urban area. Cost would be lower (approx. $10,500) for a few arterial intersections. O&M includes software upgrades, revisions, and expansion of the system.
Labor for Signal Control TM002 empty cell empty cell empty cell empty cell 486 594 2001 Costs include labor for operations (two at 50% of the time, at $100K), transportation engineer (one at 50% of the time, at $100K), update timing plans ($2K per system per month for every 10 systems), and signal maintenance technician (two at $75K). Salary cost are fully loaded prices including base salary, overtime, overhead, benefits, etc.
Hardware, Software for Traffic Surveillance TM003 20 135 165 1995 6.75 8.25 1995 Processor and software.
Integration for Traffic Surveillance TM032 20 225 275 1995 11.25 13.75 1995 Integration with other systems.
Hardware for Freeway Control TM004 5 6 9 2003 0.3 0.45 2003 Includes three workstations. O&M estimated at 5% of capital cost.
Software, Integration for Freeway Control TM007 5 180 220 2002 empty cell empty cell empty cell Software and integration, installation and one year maintenance. Software is off-the-shelf technology and unit cost does not reflect product development.
Labor for Freeway Control TM005 empty cell empty cell empty cell empty cell 225 275 2001 Labor for operations (two at 50% of $100K) and maintenance technicians (two at $75K). Salary cost are fully loaded prices including base salary, overtime, overhead, benefits, etc.
Hardware for Lane Control TM008 5 2 3 2003 0.1 0.15 2003 Includes one workstation and 19" monitor. O&M estimated at 5% of capital cost.
Software, Integration for Lane Control TM009 10 225 275 1995 11.25 13.75 1995 Software development and integration and software upgrade for controllers. Software development is fine tune adjustments for local installations. Otherwise, software is COTS.
Labor for Lane Control TM010 empty cell empty cell empty cell empty cell 90 110 2001 Labor for two operators at 50% of $100K.
Software, Integration for Regional Control TM011 10 300 400 1998 empty cell empty cell empty cell Software and integration, installation and one year maintenance. Integration with other TMC's. Software is COTS.
Real-time, Traffic Adaptive Signal Control System empty cell 10 120 150 2001 20 20 2001 The costs range is based on commercially available packages, which run on a centralized computer. The high capital cost includes software packages for graphical user interface and incident management.
Labor for Regional Control TM012 empty cell empty cell empty cell empty cell 180 220 2001 Labor for operators (two at 50% of $100K), transportation engineer (one at 50% of $100K), and maintenance contract. Salary costs are fully loaded prices including base salary, overtime, overhead, benefits, etc.
Video Monitors, Wall for Incident Detection TM013 15 57 103 2003 3 5 2003 Video wall and monitors. O&M estimated at 5% of capital cost.
Hardware for Incident Detection TM014 5 43 57 2003 2.15 2.85 2003 Includes four servers, five workstations, and two laser printers. O&M estimated at 5% of capital cost; could be higher for responsive and preventative maintenance.
Integration for Incident Detection TM025 20 90 110 1995 4.5 5.5 1995 Integration with other systems.
Software for Incident Detection TM015 5 90 110 2002 4.5 5.5 2002 Software is COTS and includes development cost. O&M is estimated at 5% of capital.
Labor for Incident Detection TM016 empty cell empty cell empty cell empty cell 630 770 2001 Labor for operators (four at $100K and one manager at $150K) and two maintenance techs at $75K.
Video Monitor for Incident Response TM017 5 0.6 1.5 2003 empty cell empty cell empty cell Includes one 19" monitor.
Hardware for Incident Response TM018 5 2 3 2003 0.1 0.15 2003 Includes one workstation. O&M estimated at 5% of capital cost.
Integration for Incident Response TM026 20 180 220 1995 empty cell empty cell empty cell Integration with other systems.
Software for Incident Response TM019 2 13.5 16.5 1995 0.675 0.825 1995 Software is COTS.
Labor for Incident Response TM020 empty cell empty cell empty cell empty cell 90 110 2001 Labor for incident management coordinator (one at $100K).
Automated Incident Investigation System empty cell 5 15 15 2001 empty cell empty cell empty cell Includes workstation, tripod, monopole antenna, Auto Integration, and AutoCAD software.
Hardware for Traffic Information Dissemination TM021 5 2 3 2003 0.1 0.15 2003 Includes one workstation. O&M estimated at 5% of capital cost.
Software for Traffic Information Dissemination TM022 5 18 22 1995 0.9 1.1 1995 Software is COTS.
Integration for Traffic Information Dissemination TM023 20 90 110 2000 4.5 5.5 1995 Integration with other systems.
Labor for Traffic Information Dissemination TM024 empty cell empty cell empty cell empty cell 90 110 2001 Labor for one operator at $100K. Salary costs are fully loaded and include base salary, overtime, overhead, benefits, etc.
Software for Dynamic Electronic Tolls TM027 5 22.5 27.5 1995 1.125 1.375 1995 Includes software installation and one year maintenance. Software is COTS.
Integration for Dynamic Electronic Tolls TM028 20 90 110 1995 4.5 5.5 1995 Integration with other systems.
Hardware for Probe Information Collection TM033 3 2 3 2003 0.1 0.15 2003 Includes one workstation. O&M estimated at 5% of capital cost.
Software for Probe Information Collection TM034 5 18 22 1995 1.8 2.2 1995 Includes software installation and one year maintenance. Software is COTS.
Integration for Probe Information Collection TM035 20 135 165 1995 13.5 16.5 1995 Integration with other systems.
Labor for Probe Information Collection TM036 empty cell empty cell empty cell empty cell 45 55 2001 Labor for one operator (four hours per day at $100K/year). Salary costs are fully loaded prices and include base salary, overtime, overhead, benefits, etc.
Software for Rail Crossing Monitor TM037 5 18 22 1995 1.8 2.2 1995 Includes software installation and one year maintenance. Software is COTS.
Integration for Rail Crossing Monitor TM038 20 90 110 1995 empty cell empty cell empty cell Integration with other systems.
Labor for Rail Crossing Monitor TM039 empty cell empty cell empty cell empty cell 45 55 2001 Operators (one at 50% of $100K). Salary costs are fully loaded prices including base salary, overtime, overhead, benefits, etc.
Road Weather Information System (RWIS) empty cell 25 25 25 1998 0.4 2.5 2001 An RWIS consists of several components: an environmental sensing station (ESS), CPU, workstation with RWIS software, and communications equipment. All components of the RWIS reside at the TMC with the exception of the ESS. See Roadside Detection subsystem for costs of ESS. Cost of the ESS ($10K–$50K) should be added to $25K listed here in order to cost out the entire system. CPU replaced every 5 years at a cost of $4K. O&M costs range includes communication, and optional weather forecast/meteorological service.

Transit Management Center (TR)
Subsystem/Unit Cost Element IDAS No.[1] Lifetime (years)[2] Low Capital Cost ($K) High Capital Cost ($K) Cost Date Low O&M Cost ($K/year) High O&M Cost ($K/year) Cost Date Notes
Basic Facilities, Comm for Large Area TR014 empty cell 4,000 4,000 1995 400 600 1995 For population >750,000. Based on purchase of building rather than leasing space. Communications includes communications equipment internal to the facility such as equipment racks, multiplexers, modems, etc.
Basic Facilities, Comm for Medium Area TR015 empty cell 3,200 3,200 1995 400 480 1995 For population <750,000 and >250,000. Based on purchase of building rather than leasing space. Communications includes communications equipment internal to the facility such as equipment racks, multiplexers, modems, etc.
Basic Facilities, Comm for Small Area TR016 empty cell 2,800 2,800 1995 400 420 1995 For population <250,000. Based on purchase of building rather than leasing space. Communications includes communications equipment internal to the facility such as equipment racks, multiplexers, modems, etc.
Transit Center Hardware TR001 5 6 9 2003 0.12 0.18 2003 Includes three workstations. O&M estimated at 2% of capital cost.
Transit Center Software, Integration TR002 20 815 1,720 1995 6 12 1995 Includes vehicle tracking and scheduling, database and information storage, schedule adjustment software, real-time travel information software, and integration. Software is COTS.
Transit Center Additional Building Space TR003 empty cell empty cell empty cell empty cell 6 9 1995 Additional space required for ITS technology – $12–$18/sq. ft., 500 sq. ft.
Transit Center Labor TR004 empty cell empty cell empty cell empty cell 50 250 1995 Labor for three staff at $75K. Salary cost are fully loaded prices including base salary, overtime, overhead, benefits, etc.
Upgrade for Auto. Scheduling, Run Cutting, or Fare Payment TR005 20 20 40 1995 0.4 0.8 1995 Processor/software upgrade, installation and one year maintenance (for processor). Software is COTS.
Integration for Auto. Scheduling, Run Cutting, or Fare Payment TR012 20 225 500 1995 empty cell empty cell empty cell Integration with other systems.
Further Software Upgrade for E-Fare Payment TR013 20 40 60 1995 0.8 1.2 1995 Software upgrade. Software is COTS. Automatic passenger counter processing software costs an additional $25K to several hundred thousand dollars depending on the system.
Vehicle Location Interface TR007 20 10 15 1995 empty cell empty cell empty cell Vehicle location interface.
Video Monitors for Security System TR008 5 3 7 2003 0.06 0.14 2003 Five per site. O&M estimated at 2% of capital cost.
Hardware for Security System TR009 5 14 19 2003 0.28 0.38 2003 Includes one server and three workstations. O&M estimated at 2% of capital cost; could be higher for preventative and responsive maintenance.
Integration of Security System with Existing Systems TR010 20 250 500 1995 empty cell empty cell empty cell Integration with other systems.
Labor for Security System TR011 empty cell empty cell empty cell empty cell 202 247 1995 Labor for three staff at $75K each. Salary cost are fully loaded prices including base salary, overtime, overhead, benefits, etc.

Toll Administration (TA)
Subsystem/Unit Cost Element IDAS No.[1] Lifetime (years)[2] Low Capital Cost ($K) High Capital Cost ($K) Cost Date Low O&M Cost ($K/year) High O&M Cost ($K/year) Cost Date Notes
Toll Administration Hardware TA001 5 4 6 2003 0.2 0.3 2003 Includes two workstations, printer, and modem. O&M estimated at 5% of capital costs.
Toll Administration Software TA002 10 40 80 1995 4 8 1995 Includes local database and national database coordination. Software is COTS.

Transit Vehicle On-Board (TV)
Subsystem/Unit Cost Element IDAS No.[1] Lifetime (years)[2] Low Capital Cost ($K) High Capital Cost ($K) Cost Date Low O&M Cost ($K/year) High O&M Cost ($K/year) Cost Date Notes
Driver Interface and Schedule Processor TV001 10 0.3 0.5 1995 0.006 0.01 1995 On-board schedule processor and database.
Cell-Based Communication Equipment TV002 10 0.15 0.25 1995 0.0075 0.0125 1995 Cell-based radio with data capacity.
GPS/DGPS for Vehicle Location TV003 10 0.5 2 2002 0.01 0.04 2002 AVL GPS/DGPS. Capital cost depends on features of unit. O&M cost (estimated at 2% of capital) is for unit maintenance and does not include annual telecom service fees.
Signal Preemption Processor TV004 10 0.3 0.6 1995 0.006 0.01 1995 On-board schedule processor and database. Complement to IDAS elements RS004 and RS005.
Signal Preemption/Priority Emitter empty cell empty cell 0.5 2.1 2003 empty cell empty cell empty cell Data-encoded emitter; manually initiated. Complement to Roadside Signal Preemption/Priority (see Roadside Control subsystem).
Preemption/Priority Transponder empty cell empty cell 0.075 0.075 2000 empty cell empty cell empty cell Passive transponder mounted on underside of transit vehicle. Requires transit priority system at the Transit Management Center.
Trip Computer and Processor TV005 10 0.1 0.15 1995 0.002 0.003 1995 On-board processor for trip reporting and data storage.
Security Package TV006 10 4.2 7 1995 0.21 0.265 1995 On-board CCTV surveillance camera and hot button. The high capital cost represents a common installation of a digital event recorder system.
Electronic Farebox TV007 10 0.8 1.5 1995 0.04 0.075 1995 On-board flex fare system DBX processor, on-board farebox, and smart card reader.
Automatic Passenger Counting System empty cell 10 1 10 2003 empty cell empty cell empty cell Low cost reflects the APC system as an add-on to an existing route scheduling or tracking system. High cost reflects the APC system as a stand alone installation. Cost is per vehicle and includes installation.

Commercial Vehicle Administration (CA)
Subsystem/Unit Cost Element IDAS No.[1] Lifetime (years)[2] Low Capital Cost ($K) High Capital Cost ($K) Cost Date Low O&M Cost ($K/year) High O&M Cost ($K/year) Cost Date Notes
Commercial Vehicle Admin Hardware CA001 5 6 9 2003 0.12 0.18 2003 Includes three workstations. O&M estimated at 2% of capital cost.
Commercial Vehicle Admin Software, Integration CA002 20 200 220 1995 4 4.4 1995 Includes processor and integration. Software is COTS.
Commercial Vehicle Admin Labor CA003 empty cell empty cell empty cell empty cell 270 330 2003 Labor for four staff at $75K (average). Salary costs are fully loaded prices including base salary, overtime, overhead, benefits, etc.
Software Upgrade for Electronic Credential Purchasing CA004 20 60 140 1995 1.2 2.8 1995 Electronic credentials purchase software, database and management for post-trip processing and E-credentials.
Software Upgrade for Inter-Agency Info Exchange CA005 20 20 40 1995 0.4 0.8 1995 Processor and integration add-on. Software is COTS.
Added Labor for Inter-Agency Info Exchange CA006 empty cell empty cell empty cell empty cell 67 82 1995 Labor for one staff at $75K (average). Salary cost are fully loaded prices including base salary, overtime, benefits, etc.
Software Upgrade for Safety Administration CA007 20 40 80 1995 0.8 1.6 1995 Database add-on, software, and integration. Software is COTS.

Commercial Vehicle Check Station (CC)
Subsystem/Unit Cost Element IDAS No.[1] Lifetime (years)[2] Low Capital Cost ($K) High Capital Cost ($K) Cost Date Low O&M Cost ($K/year) High O&M Cost ($K/year) Cost Date Notes
Check Station Structure CC001 20 50 75 1995 empty cell empty cell empty cell Roadside structure—mainline w/ lane indicator signals.
Signal Board CC002 10 10 15 1995 1 1.5 1995 Roadside signal board.
Signal Indicator CC003 20 5 10 1995 0.25 0.5 1995 Signal indicator system.
Roadside Beacon CC004 10 5 8 1995 0.5 0.8 1995 Roadside beacon used for electronic screening (not included in roadside subsystem). Beacon repair/replacement.
Wireline to Roadside Beacon CC005 20 10 20 1995 empty cell empty cell empty cell Dedicated wireline communication from beacon to roadside (one mile upstream).
Check Station Software, Integration CC006 20 180 215 1995 empty cell empty cell empty cell Software, processor and integration.
Check Station Hardware CC007 5 2 3 2003 0.04 0.06 2003 Includes one workstation. O&M estimated at 2% of capital cost.
Safety and Fitness Electronic Records (SAFER) Data Mailbox empty cell empty cell 7.5 9.2 1999 0.44 0.66 1999 Includes portable computer with printer and wireless Internet modem to download, record, and upload carrier safety database records at field locations or check stations.
Detection System CC008 10 50 75 1995 2.5 3.75 1995 Commercial vehicle communication interface and communication device (cell based radio).
Software Upgrade for Safety Inspection CC009 20 40 80 1995 0.8 1.6 1995 Safety database add-on and result writing to vehicle tag processor add-on. Software is COTS.
Handheld Safety Devices CC010 5 3 5 1995 0.3 0.5 1995 For commercial vehicle inspection. The devices either measure data themselves or read data from the vehicle. Three per location.
Software Upgrade for Citation and Accident Recording CC011 20 20 40 1995 1 2 1995 Software add-on for recording of citation and accident information to the commercial vehicle.
Weigh-In-Motion Facility CC012 10 14 21 1995 1.4 2.1 1995 Includes WIM fixed load cell and interface to roadside facility. Software is COTS.
Wireline to Weigh-In-Motion Facility CC013 10 1 2 1995 0.1 0.2 1995 Wireline communication (local line).

Commercial Vehicle On-Board (CV)
Subsystem/Unit Cost Element IDAS No.[1] Lifetime (years)[2] Low Capital Cost ($K) High Capital Cost ($K) Cost Date Low O&M Cost ($K/year) High O&M Cost ($K/year) Cost Date Notes
Electronic ID Tag CV001 10 0.65 1.1 1995 0.013 0.022 1995 Includes ID tag, additional software and processing, and database storage. Software is COTS.
Communication Equipment CV002 10 1.15 2.25 1995 0.0075 0.0125 1995 Commercial vehicle communication interface and communication device (cell-based radio).
Central Processor and Storage CV003 10 0.3 0.5 1995 0.006 0.01 1995 Equipment on board for the processing and storage of cargo material.
GPS/DGPS CV004 10 0.5 1.8 2002 0.01 0.036 2002 GPS for vehicle location. Capital cost depends on features of unit. O&M cost (estimated at 2% of capital) is for unit maintenance and does not include annual telecom service fees.
Driver and Vehicle Safety Sensors, Software CV005 10 1.1 2.2 1995 0.04 0.08 1995 Additional software and processor for warning indicator and audio system interface, and onboard sensors for engine/vehicle and driver. Software is COTS.
Cargo Monitoring Sensors and Gauges CV006 10 0.17 0.35 1995 0.017 0.035 1995 Optional on-board sensors for measuring temperature, pressure, and load leveling.
Electronic Cargo Seal Disposable empty cell empty cell 0.01 0.025 2003 empty cell empty cell empty cell Cost for a disposable radio frequency identification (RFID) E-seal that provides a complete and accurate audit trail of seal status during transport. Low is for passive, and high is for active E-seal.
Electronic Cargo Seal Reusable empty cell empty cell 0.035 0.44 2002 empty cell empty cell