ITS Projects Book January 2003


Project Title:   STATEWIDE TRANSPORTATION OPERATIONS CENTER
     
Project Status:   In Progress
     
Project Type:   Deployment/Integration
     
Project Description:   This project is the FY 2002 ITS Integration Program Kentucky Statewide earmark. The project objective is the construction and activation of a Statewide Transportation Operations Center (STOC). The STOC will serve as the Kentucky Transportation Cabinet's focal point for dispatching Kentucky Vehicle Enforcement Officers, coordinating snow/ice removal, disaster reaction, incident management, delivering traveler information, and serving as the Commonwealth's back-up Emergency Operations Center.
     
Project Location:   Commonwealth of Kentucky
     
Project Partner(s):   FHWA, Kentucky Transportation Cabinet
     
Project Start Date:   September 2002
     
Project End Date:   April 2004
     
Estimated Total ITS Funds:   $1,654,637
     
Estimated Total Project Cost:   $3,309,274

Project Contacts:    
     
Brent Sweger
FHWA Kentucky Division, HDA-KY
(502) 223-6743
Ext.
Charles Knowles
Kentucky Transportation Cabinet
(502) 564-4556
Ext.



U.S. Department of Transportation, Intelligent Transportation Systems