| Project Title: |
METRO ARTERIAL MANAGEMENT SYSTEM SOFTWARE UPGRADE AND MTOC/RTMC SYSTEM INTEGRATION |
|
| Project Status: | In Progress | |
| Project Type: |
Deployment/Integration |
|
| Project Description: | This project is the FY 2001 ITS Integration Program earmark for Nashville, TN. The principal project objectives are to acquire the software/hardware components to support integration of Metropolitan Nashville's ITS-related projects into one comprehensive Arterial Management System. Once deployed, the second objective is to integrate the Arterial Management System with Tennessee DOT's Freeway Management System. The deployment of the Arterial Management System will result in achieving real-time traffic control capabilities through a centralized signal system, arterial surveillance, incident detection and management, and inter-agency communication. | |
| Project Location: | Nashville, Tennessee | |
| Project Partner(s): | FHWA, FTA, Tennessee DOT, Metropolitan Government of Nashville and Davidson County | |
| Project Start Date: | September 2001 | |
| Project End Date: | June 2003 | |
| Estimated Total ITS Funds: | $396,807 | |
| Estimated Total Project Cost: | $793,614 |
| Project Contacts: | ||
Michael Smart |
FHWA Tennessee Division, HPR-TN |
(615) 781-5775 |
Ext. |
Mark Macy |
Dept. of Public Works |
(615) 862-8764 |
Ext. |