ITS - Intelligent Transportation Systems Report ITS Home Page

4. Institutional Issues and Lessons Learned

In addition to the evaluation areas previously discussed, the evaluation team also worked with the project stakeholders to document institutional challenges, technical issues, and lessons learned encountered throughout deployment and operation of these systems. The information was gathered through a variety of methods, including reviewing meeting minutes and conducting formal and informal interviews with stakeholders and project partners.

4.1 Deployment Lessons Learned

One lesson reported with regard to technology is that it is important to conduct a field study during the design engineering phases prior to deployment of any project relying on radio frequency or other similar communications technologies. Unique capital requirements resulting from unforeseen field conditions is quite a common reality for ITS applications. Metra learned early on into the construction process (during the Radio Frequency Field Study, which they called for in the contractual specifications) that installation of repeater poles at various sites would be required to ensure uninterrupted, seamless wireless transmission between data controllers and signs. When relying on radio transmissions, topographical encumbrances and other radio transmission interferences should be expected. In the case of the Metra project, it was found that a highway vehicle weigh station located within the project radius would cause radio frequency interference.

It is also important to realize that permit issues can require a significant amount of time, particularly if multiple jurisdictions are involved; the Chicago project stakeholders experienced delays in obtaining some of their permits.

4.2 Technology Lessons Learned

One lesson reported with regard to technology is that, depending on what is available off-the-shelf, consider customized software if the project budget can accommodate it. At the time that Montgomery County began their project, they were not aware of any product on the market that did exactly what they needed. Since they did not have a large enough budget to have software designed for the specific purpose of this project, they had to modify commercial-off-the-shelf (COTS) traffic control software, which was not ideal. Some specific limitations that the county faced as a result of not being able to have customized software are as follows:

Another lesson is that it is important to be aware of the inherent limitations of the technology. Specific examples of this are as follows:

4.3 Operations and Maintenance Lessons Learned

An important consideration with regard to operations and maintenance is that, for this type of system to be reliable in the long run, staff should expect that they will likely need to change the settings manually at times. For example, Montgomery County found that the fill rate slowed significantly during the summer months when traffic is typically lighter; as a result, the county had to adjust the system's algorithms a few times a year to accommodate this variation. In order to do this, it is critical to ensure that those who will be responsible for monitoring and maintaining the system are trained on how to use the equipment if they were not involved in the software development and/or testing.

Another important consideration is that a monitoring system that is built into the design can save time and help the project team ensure system reliability. The Montgomery County staff elected to install a camera on the top of the Glenmont Garage to aid in remote monitoring of the system (see camera views in Figure 50[37]), and they have found it to be extremely useful in monitoring the system on a regular basis. They generally check in on the system at least once a week to see if it appears to working properly based on how full the top level of the garage looks as compared to how many spaces the system shows to be remaining.

For Metra, the remote user interface consists of a dedicated laptop that provides the information that is currently on each sign, a configuration of the lot assemblies, and also an error-checking mechanism (errors are indicated with a red dot). It also allows the user to update or shut off the signs remotely. Currently, the system does not fail often but it requires constant monitoring. They find that it works best to leave the system up and running consistently in the background.

Panoramic photo of three-tiered parking garage
Figure 50. Camera View of Parking Garage for Monitoring Montgomery County System.

It is critical to identify up front what agency (and what staff position in particular) will ultimately be responsible for monitoring and maintaining the system after it is in place (particularly as maintenance can be costly depending on the system). This could be the contractor who designed and/or installed the system if desired. It is also important to clearly denote where and how all maintenance activities should be documented. As an example, the Chicago project's maintenance schedule calls for the following activities:[38]

One lesson to keep in mind regarding maintenance costs is that RTA and Metra have found that the solar batteries need to be replaced quite often. One of their signs is solar powered because there was no electrical line available at the sign location. At the time of design, it appeared that it was more costly to run an electrical line to the sign than to use a battery. In retrospect, however, the batteries required by the solar powered sign have been very expensive, and have less capacity than the electrical signs. Therefore, in the long run, extending the electrical line is likely to have been more cost effective.

A unique issue that the Chicago stakeholders faced was that at the time of their initial design, there were no American companies that created or manufactured this type of system. The project team contracted with a European developer since these types of systems were more prevalent in Europe at the time. Consequently, the team encountered issues with some of the manuals and programming being in another language, making software customization and software updates a challenge.

4.4 Contracting Lessons Learned

An important lesson with regard to contracting is that, in retrospect, the Chicago team feels that the lump sum contracting vehicle utilized may have not been the best choice for this type of system. The selected type of contract used meant that the city had to select the lowest bidder and it also meant that the contractor did not have an incentive to finish the project quickly once encountering problems. Looking back, the team believes that a cost plus fixed fee contract may have been more appropriate as this type of arrangement would have given vendors an incentive to complete the deployment more quickly, and it would have allowed the team to make a qualifications-based selection.

Another contracting lesson that the stakeholders passed on is that they feel that a design-build model might be more appropriate for this type of technology than a design-bid-build model.

4.5 Institutional Lessons Learned

It is also important to keep all potentially affected organizations informed of work planned as part of the project. Some of the stakeholders felt that without close coordination, their projects would not have been possible. They indicated that active coordination among the various levels of government helped stave off unnecessary future costs and potential relocation of systems. Below are some examples of coordination that the Chicago project stakeholders faced throughout the course of their project deployment:

The most important institutional lesson learned that both project teams passed on to the evaluation team is that it is critical to involve all appropriate stakeholders in a formal and collaborative manner throughout the planning, deployment, and operations phases of a multi-jurisdictional project such as this. Parking management systems are often integrated into urban or neighborhood environments and, as such, take time to deploy and require a diverse group of stakeholders. Late-breaking or unresolved stakeholder concerns can stall the effort indefinitely. To prevent stalling, the project stakeholders should obtain formal endorsement from the leadership of all jurisdictions involved. The mayor or county executive should seek city or county council endorsement and should designate a staff member or a specific public agency as their organization's champion for the system. This champion will exercise executive leadership with in the stakeholder group and will represent the project in any public policy discussions and funding processes. Identify and define the role of the champion and ensure that the project stakeholders work from a formal charter that binds the member organizations to the effort and provides a forum for resolution of issues.

  1. Composite photo series compiled from photo series captured by camera mounted on Glenmont Parking Garage, courtesy of Montgomery County.
  2. Metra Parking Management System Maintenance Schedule obtained from Metra December 12, 2007.

Previous | Next